Team

 

The Requirement Traceability option shows the last run execution status. If I had pulled 10 test cases which was ran in a previous test set and only 3 of them are executed in the current test set, then the requirement traceability will have the status for 10 test cases (3 current test set status and 7 previous test set status). Is there an option by which the requirement traceability shows the test case status in the latest build. For example, if I am pulling 10 test cases of 20 to a new test set, then the status for the 10 should be changed to No Run. 