How can we get visibility of what makes up costs in a Financial Summary.

In a Financial Summary \ Cost Details we can see Labour - Employee and contractor totals

Can we setup PPM to break the contractor costs out by the contractor resource (source of the cost)?

 

| CMC (HP PPM) Administration| Change Portfolio Office | Change Division |
| Bendigo and Adelaide Bank Limited|PO Box 480 Bendigo Vic 3552|
| email: changeportfolioofficemailbox@bendigobank.com.au |
Honored Contributor
Utkarsh_Mishra
Posts: 713
Registered: ‎07-13-2010
Message 2 of 3 (177 Views)

Re: Visibility of what makes up costs in a Financial Summary

For this you need to create the COST CATEGORY i.e add the Labor category in Validation "CST - Budget Labor Category"; example Contractor, Contractor-Offshore, Employee.... etc.

 

Once done you can go to Resource Profile and set the Cost Category for the resources, based on this Cost Category PPM rollup services will create the Financial Summary Budget lines and will trach the Forecast and Actuals.

 

This way you can segrigate the contractor cost and it will be tracked in seperate budget line.

Cheers..
Utkarsh Mishra

-- Remember to give Kudos to answers! (click the KUDOS star)
ur1
Occasional Advisor
ur1
Posts: 15
Registered: ‎03-09-2013
Message 3 of 3 (174 Views)

Re: Visibility of what makes up costs in a Financial Summary

Thanks for the tip Utkarsh

 

We will try this.

 

Wayne

| CMC (HP PPM) Administration| Change Portfolio Office | Change Division |
| Bendigo and Adelaide Bank Limited|PO Box 480 Bendigo Vic 3552|
| email: changeportfolioofficemailbox@bendigobank.com.au |
The opinions expressed above are the personal opinions of the authors, not of HP. By using this site, you accept the Terms of Use and Rules of Participation.