Milestone duration problem after migrating msp projects' work plan (262 Views)
Reply
Frequent Advisor
kndlny
Posts: 62
Registered: ‎10-29-2011
Message 1 of 3 (262 Views)

Milestone duration problem after migrating msp projects' work plan

Hi,

 

We are using PPM v9.10 and we have migrated msp projects' work plans to ppm work plans.

 

After migration we have noticed that most milestone durations are 1 day instead of 0.

 

We have tried to update scheduled durations of milestones on the work plan but it did not update the parent tasks; so did the mass update from db.

 

We are supposed to specify some parameters in web service? Because manual update would cost us so much effort.

 

Thanks,

Honored Contributor
Celil
Posts: 548
Registered: ‎03-17-2011
Message 2 of 3 (236 Views)

Re: Milestone duration problem after migrating msp projects' work plan

Hi,

I'm not agree with you about web services make it easier your updates. DB mass update more fast and easy but dangerous.
Web sercvices are slow and hard to programe but formal way.
Celil

IT Governance Professional
& PPM Solution Architect
director@ppmdiary.com
director@isframeworks.com
Frequent Advisor
kndlny
Posts: 62
Registered: ‎10-29-2011
Message 3 of 3 (220 Views)

Re: Milestone duration problem after migrating msp projects' work plan

Hi Celil,

 

Thanks for your reply.

 

We will probably go with the DB.

 

Thanks