I've seen this frequently but I don't know why. 

 

I am in Sprint Planning and I can't seem to move from Sprint to Sprint - it is greyed out.  And it also tells me "There are no active members for this sprint" - screen print is attached. 

 

What is the cause of this?  How to I stop if from happening? Is this a Defect?

 

After I move around in AGM for a bit, I go back and the members are there - did I do something to make it change?

 

Thanks in advance...Deb

 

Please use plain text.
Frequent Advisor
rshmiel
Posts: 42
Registered: ‎03-12-2012
Message 2 of 7 (284 Views)

Re: Sprint Backlog - No Active Members for this Sprint

Hi Deb,

 

Please navigate to

configuration >  Release > Choose the right Release > Additional Setting 

Can you please check if the "Release Working Days:" are set?

 

Thanks

Ronen

 

Please use plain text.
Frequent Advisor
DebKelchner
Posts: 55
Registered: ‎10-17-2012
Message 3 of 7 (275 Views)

Re: Sprint Backlog - No Active Members for this Sprint

No, the Release Working Days are not set...so I assume they should be?

Please use plain text.
Frequent Advisor
DebKelchner
Posts: 55
Registered: ‎10-17-2012
Message 4 of 7 (270 Views)

Re: Sprint Backlog - No Active Members for this Sprint

But...even though I added the days, the problem still exists. And again, once I navigate in and out a few times, the members eventually show up.

Please use plain text.
Frequent Advisor
rshmiel
Posts: 42
Registered: ‎03-12-2012
Message 5 of 7 (269 Views)

Re: Sprint Backlog - No Active Members for this Sprint

Hi DebKelchner,

 

Yes it should, please set the working days and check if it solve the probelm....

 

Thanks

Ronen

Please use plain text.
Advisor
Omsracer
Posts: 25
Registered: ‎09-06-2011
Message 6 of 7 (254 Views)

Re: Sprint Backlog - No Active Members for this Sprint

I have the same problem.  The release days seem to being removed and going back in and 'ticking' them does not solve this problem.

Please use plain text.
Advisor
Omsracer
Posts: 25
Registered: ‎09-06-2011
Message 7 of 7 (253 Views)

Re: Sprint Backlog - No Active Members for this Sprint

Cannot set the working days as after ti8cking the relevant days and clicking 'Save'   the update does not work despite the 'Item successfully saved' message.