Configurable task status

"New", "In Progress" and "Complete" is a great simple default task status.  But one of our teams has implemented a working agreement that they always do a peer-review of any task before it is called complete and they use this on their taskboard to help team members self-manage peer-reviews.

 

This can be accommodated in a number of online Kanban tools and other competing products.  I can't find a way to help this team implement this process using the AgM taskboard.  Is their a way to do this?